Use this checklist to prepare a complete, code-accurate RFQ for custom ASME pressure vessels, jacketed reactors, and specialty containers.
mrxmfg.com
info@mrxmfg.com
2026 Edition
Why this matters: An incomplete RFQ produces bids that are either padded with contingency or structurally non-comparable. Specifying design pressure, applicable code, material, NDE scope, and documentation requirements upfront eliminates the most common causes of bid spread and post-award change orders.
ASME code: Section VIII Division 1 / Division 2 / Section III (specify which applies)
ASME stamp required: U stamp / U2 stamp / N stamp / none (specify)
Canadian Registration Number (CRN) required — list provinces
State/jurisdictional registration requirements (list states if applicable)
Third-party inspection required — specify Authorized Inspection Agency (AIA)
National Board registration required (NB stamp on nameplate)
Design pressure (internal): ___ psig
Design pressure (external/full vacuum): Yes / No
Design temperature (maximum operating): ___ °F
Design temperature (minimum): ___ °F (for low-temperature or cryogenic service)
Hydrotest or pneumatic test pressure: ___ psig (if deviation from code default required)
Radiography category: Full / Spot / None (specify per joint)
Fluid(s) in contact with vessel internals (name each, including cleaning agents)
Fluid phase: liquid / gas / two-phase
Corrosive, toxic, or lethal service: Yes / No (if yes, specify)
Hydrogen service or other specialized environment: Yes / No
Cyclic pressure or thermal cycling service: Yes / No
Shell and head material (specify SA designation if known, e.g. SA-516-70)
Nozzle and flange material
Internals material (baffles, supports, trays, agitator, coils)
Weld filler material requirements or restrictions
Impact testing required: Yes / No — if yes, specify MDMT
Mill certifications required: Yes / No — EN 10204 Type 3.1 or 3.2
Shell inside diameter (ID): ___ inches
Shell nominal length / tangent-to-tangent length: ___ inches
Head type: 2:1 ellipsoidal / hemispherical / ASME F&D / flat (specify top and bottom)
Orientation: vertical / horizontal (specify support type: legs, saddles, lugs)
Number of nozzles — list each: size, rating (ANSI 150/300/600), facing (RF/FF/RTJ), orientation
Manway required: Yes / No — if yes: size, orientation, hinge or davit
Agitator/mixer: Yes / No — if yes: type, speed, shaft seal type
Heating/cooling jacket: Yes / No — if yes: type (conventional, dimple, half-pipe), design pressure
Internal coils: Yes / No — if yes: material, design pressure, coil geometry
Internal lining (glass, rubber, PTFE, Hastelloy, etc.): Yes / No
Removable or cleanable internals required: Yes / No
Spray nozzles or CIP spray balls: Yes / No — specify flow requirement
External finish: mill / sandblast / primer / paint (specify RAL/color if applicable)
Internal finish: mill / #4 polish / #4 electropolish / specify Ra ≤ ___ µin
Passivation required: Yes / No — specify standard (ASTM A967 citric or nitric)
Electropolish required: Yes / No — specify Ra requirement (e.g. ≤ 20 µin / ≤ 0.5 µm)
Sanitary/hygienic construction (3-A, ASME BPE): specify applicable standard
Product contact surface documentation (certificates, profilometry reports): Yes / No
Radiography (RT): per code minimum / spot / full / none (specify joints)
Ultrasonic testing (UT): Yes / No — specify scope
Magnetic particle (MT) or liquid penetrant (PT): Yes / No — specify scope
Post-weld heat treatment (PWHT): per code / required / waived — specify basis
Charpy impact testing: per code / required — specify minimum temperature
Hardness testing required: Yes / No
ASME U1 or U1A data report (mandatory for U-stamped vessels)
Material certifications (MTRs) — specify retention requirement
Weld procedure specifications (WPS) and procedure qualification records (PQR)
Weld map and weld traveler
NDE reports (RT film, UT reports, MT/PT records)
Hydrostatic / pneumatic test report and pressure chart
As-built drawing and dimensional inspection report
Required delivery date / lead time constraint (specify hard deadline if applicable)
FOB point: fabricator shop / job site / other (specify)
Shipping constraints: maximum transport width / height / weight
Rigging lugs required: Yes / No — specify lift weight and rigging angle
Preservation and packaging requirements (nitrogen purge, desiccant, crating)
Owner-furnished items (OFI) to be incorporated: list any customer-supplied materials
Use this checklist to prepare your RFQ package, then submit it through our quote request form or send directly to our engineering team. The more complete your RFQ, the faster we can return a detailed proposal.